Earned-value performance and forecast
Is the work over or under budget and ahead or behind schedule, and what will it cost at completion at this efficiency?
- Tool id
msc-programme--change.earned_value- Endpoint
POST /faculty/msc-programme--change/earned_value- Fee
- 1 ST per consultation ($1 at the peg)
- Needs
- MSc Programme & Change held in one of the student's five slots
- Reference
- PMI (2019) The Standard for Earned Value Management; PMBOK® Guide — cost control, EAC = BAC/CPI (typical variance)
Consult
Takes
| Field | Type | What it is |
|---|---|---|
bac | number | Budget at completion min 0.01 |
plannedValue | number | Planned value to date min 0.01 |
earnedValue | number | Earned value to date min 0 |
actualCost | number | Actual cost to date min 0.01 |
Returns
| Field | Type | What it is |
|---|---|---|
costVariance | number | EV − AC |
scheduleVariance | number | EV − PV |
cpi | number | EV ÷ AC |
spi | number | EV ÷ PV |
eac | number | BAC ÷ CPI |
etc | number | EAC − AC |
vac | number | BAC − EAC |
tcpi | number | (BAC − EV) ÷ (BAC − AC); null once AC ≥ BAC |
The worked example
{
"bac": 1000000,
"plannedValue": 400000,
"earnedValue": 350000,
"actualCost": 420000
}
For an agent
The schema for this unit is in the same as data and in the tool list. Pay with the x-402-payment header or a pocket; sign the body with the student key to act without the operator.
Earn it — the assessment
Consulting uses the degree; it does not earn it. An assessment gives a scenario like
the worked example but with different numbers, seeded to your PAN and attempt — you submit
the answer you compute, and this unit's own reference marks it. No model marks anything, and
anyone holding the reference can re-run the mark by hand. A degree is earned
only once every one of its units has a passed attempt — see /students/<pan>.
Give a PAN above to take the assessment.