  "tool": "msc-programme--change.earned_value",
  "name": "Earned-value performance and forecast (CDU-BUS-PCM-900)",
  "answers": "Is the work over or under budget and ahead or behind schedule, and what will it cost at completion at this efficiency?",
  "degree": {
    "id": "competency:msc-programme--change",
    "code": "CDU-BUS-PCM-900",
    "name": "MSc Programme & Change",
    "version": "1.0.0"
  },
  "reference": "PMI (2019) The Standard for Earned Value Management; PMBOK® Guide — cost control, EAC = BAC/CPI (typical variance)",
  "endpoint": "/faculty/msc-programme--change/earned_value",
  "feeSt": 1,
  "inputSchema": {
    "type": "object",
    "required": [
      "pan",
      "bac",
      "plannedValue",
      "earnedValue",
      "actualCost"
    ],
    "properties": {
      "pan": {
        "type": "string",
        "description": "The student PAN — the degree must be held in one of its five slots",
        "pattern": "^[0-9 ]{16,19}$"
      },
      "bac": {
        "type": "number",
        "description": "Budget at completion",
        "minimum": 0.01
      },
      "plannedValue": {
        "type": "number",
        "description": "Planned value to date",
        "minimum": 0.01
      },
      "earnedValue": {
        "type": "number",
        "description": "Earned value to date",
        "minimum": 0
      },
      "actualCost": {
        "type": "number",
        "description": "Actual cost to date",
        "minimum": 0.01
      }
    },
    "additionalProperties": false
  },
  "outputSchema": {
    "type": "object",
    "required": [
      "costVariance",
      "scheduleVariance",
      "cpi",
      "spi",
      "eac",
      "etc",
      "vac",
      "tcpi"
    ],
    "properties": {
      "costVariance": {
        "type": "number",
        "description": "EV − AC"
      },
      "scheduleVariance": {
        "type": "number",
        "description": "EV − PV"
      },
      "cpi": {
        "type": "number",
        "description": "EV ÷ AC"
      },
      "spi": {
        "type": "number",
        "description": "EV ÷ PV"
      },
      "eac": {
        "type": "number",
        "description": "BAC ÷ CPI"
      },
      "etc": {
        "type": "number",
        "description": "EAC − AC"
      },
      "vac": {
        "type": "number",
        "description": "BAC − EAC"
      },
      "tcpi": {
        "type": "number",
        "description": "(BAC − EV) ÷ (BAC − AC); null once AC ≥ BAC"
      }
    },
    "additionalProperties": false
  },
  "example": {
    "bac": 1000000,
    "plannedValue": 400000,
    "earnedValue": 350000,
    "actualCost": 420000
  }
}