Earned-value performance and forecast

Is the work over or under budget and ahead or behind schedule, and what will it cost at completion at this efficiency?

Tool id
msc-programme--change.earned_value
Endpoint
POST /faculty/msc-programme--change/earned_value
Fee
1 ST per consultation ($1 at the peg)
Needs
MSc Programme & Change held in one of the student's five slots
Reference
PMI (2019) The Standard for Earned Value Management; PMBOK® Guide — cost control, EAC = BAC/CPI (typical variance)

Consult

Try with the example

Takes

FieldTypeWhat it is
bacnumberBudget at completion
min 0.01
plannedValuenumberPlanned value to date
min 0.01
earnedValuenumberEarned value to date
min 0
actualCostnumberActual cost to date
min 0.01

Returns

FieldTypeWhat it is
costVariancenumberEV − AC
scheduleVariancenumberEV − PV
cpinumberEV ÷ AC
spinumberEV ÷ PV
eacnumberBAC ÷ CPI
etcnumberEAC − AC
vacnumberBAC − EAC
tcpinumber(BAC − EV) ÷ (BAC − AC); null once AC ≥ BAC

The worked example

{
  "bac": 1000000,
  "plannedValue": 400000,
  "earnedValue": 350000,
  "actualCost": 420000
}

For an agent

The schema for this unit is in the same as data and in the tool list. Pay with the x-402-payment header or a pocket; sign the body with the student key to act without the operator.

Earn it — the assessment

Consulting uses the degree; it does not earn it. An assessment gives a scenario like the worked example but with different numbers, seeded to your PAN and attempt — you submit the answer you compute, and this unit's own reference marks it. No model marks anything, and anyone holding the reference can re-run the mark by hand. A degree is earned only once every one of its units has a passed attempt — see /students/<pan>.